Finishes · The workhorse finish on B7 studs

Phosphate and oil

Phosphating grows a layer of fine manganese or zinc phosphate crystals on the steel in an acid bath, and the crystals hold oil. The finish is grey to black. Oiled, it protects studs and nuts in storage and transit, and it is the base that PTFE coatings go over. It is applied by outside Houston processors.

OIL (CLASS 2)AMANGANESE (TYPE M) OR ZINC (TYPE Z)PHOSPHATE CRYSTALSSTEELLAYERS NOT TO SCALEDETAIL A · CRYSTALS HOLD THE OILOILCRYSTALSSTEELEXPECTED THICKNESS (MIL-DTL-16232):TYPE M 5–10 µm · TYPE Z 5–15 µmTHE REQUIREMENT IS COATING WEIGHT:M 16 g/m² MIN · Z 11 g/m² MINFINISHPHOSPHATE AND OILSPECMIL-DTL-16232 TYPE M OR Z · ISO 9717
Section through a phosphated thread: a layer of phosphate crystals, typically 5 to 10 µm for manganese (5 to 15 µm for zinc), holding a film of oil.
At a glance
SpecificationDoD-P-16232 / MIL-DTL-16232 · ISO 9717
ThicknessTypically 5 to 10 µm (manganese) or 5 to 15 µm (zinc); the thread fit allows for it
Best forA193 B7 studs with A194 2H nuts, and A320 L7 studs with A194 Grade 7 nuts, shipped plain, and as the base under PTFE
How it's applied

Degrease, blast, phosphate, rinse, oil.

  1. STEP 01

    Degrease

    After all machining and forming is finished, the parts are cleaned by solvent, vapour, alkaline or emulsion cleaning.

  2. STEP 02

    Blast

    Abrasive blasting removes rust and scale and is required before heavy phosphating unless the drawing says otherwise. The parts go straight into the phosphate after it.

  3. STEP 03

    Phosphate

    The parts are immersed in a manganese (Type M) or zinc (Type Z) phosphate bath, whose acid and iron content is checked every four hours.

  4. STEP 04

    Rinse and seal

    A cold running-water rinse follows before the parts can dry, then a sealer rinse for Classes 1 to 3.

  5. STEP 05

    Relieve if hard

    Steel of 39 HRC and above is held at 210 to 225 °F (98 to 107 °C) for at least 8 hours, or rested for 120 hours, so hydrogen can escape.

  6. STEP 06

    Oil

    For Class 2, oil or rust preventive is applied and the surplus is spun or drained off.

Where it's the wrong choice
  • Light protection: bare phosphate need only pass 1.5 hours (Type M) or 2 hours (Type Z) of salt spray, and oiled Class 2 48 hours (M) or 72 hours (Z). The oil or coating on top gives most of the protection.
  • Heat: manganese phosphate should not be exposed above 250 °F (121 °C), or zinc phosphate above 200 °F (93 °C).
  • Zinc phosphate should not be used where it will contact alkaline materials.
  • Not for surfaces that must stay highly polished after coating.

Finishes are applied by outside coaters and platers in Houston, to the specification on the order.

On the thread

A thin crystal layer the fit has to allow for.

Phosphate is not zero thickness. MIL-DTL-16232 expects 5 to 10 µm for manganese and 5 to 15 µm for zinc, and requires the parts to meet their drawing dimensions after coating, with an allowance for the build-up. The specification's requirement is coating weight; the thickness figures are a guide.

The crystals are friable, so a tight fit can be assembled by forcing it or wiping off the surplus.

Phosphating is an acid process. The specification relieves steel of 39 HRC and above; B7 and L7 studs and 2H and Grade 7 nuts, at 35 HRC maximum, are below that line. On friction, oiled manganese phosphate helps parts run in. The chemically converted Class 4 is recommended for reducing sliding friction, and it narrows the spread of torque against tension on threaded fasteners.

Specifications

Designations and classes.

MIL-DTL-16232, Type M or ZHeavy manganese (M) or zinc (Z) phosphate: at least 16 g/m² coating weight for M (11 g/m² when specified) and 11 g/m² for Z.
Classes 1 to 41 supplementary treatment as specified; 2 oil or rust preventive; 3 no supplementary treatment; 4 chemically converted, may be dyed.
ISO 9717The international standard for phosphate conversion coatings on metals (2024 edition).
DOD-P-16232An earlier designation of the same specification, still seen on drawings.
Questions

Phosphate and oil: common questions.

Does phosphate change the thread size?

Slightly. Manganese phosphate is expected to be 5 to 10 µm thick and zinc phosphate 5 to 15 µm. The thread fit has to allow for it, and the friable crystals can be wiped or forced off where a fit is tight.

How long does phosphate and oil last?

It is meant for storage and transit. Oiled manganese phosphate must pass 48 hours of salt spray and oiled zinc phosphate 72 hours (MIL-DTL-16232). A PTFE topcoat over the phosphate adds far more protection.

Manganese or zinc?

Manganese (Type M) stands up better to alkaline conditions. Zinc (Type Z) is used where paint and oil both go on, and to prevent galling in cold extrusion and deep drawing.

Do B7 studs need a bake after phosphating?

No. The relief treatment is for steel of 39 HRC and above, and B7 is 35 HRC maximum.

Other finishes

Compare with.

All finishes →
DETAIL ANUTSTUDNUT TAPPED OVERSIZEAGREED WITH THE COATERDETAIL A · AT THE CREST · NOT TO SCALENUTCOATED THE SAMECLEARANCEPTFE FLUOROPOLYMER FILMABOUT 1 MIL (25 µm), TYPICALPHOSPHATE BASEZINC OR MANGANESE, CRYSTALLINESTUDONE WIDELY USED GRADE:−60 TO 350 °F (−50 TO 175 °C) CONTINUOUS400 °F (204 °C) INTERMITTENTFINISHPTFE FLUOROPOLYMER OVER PHOSPHATESPECCUSTOMER SPEC · MIL-DTL-16232 BASE
Low friction, easy break-out, the oil and gas standard

PTFE / fluoropolymer coating

A thin fluoropolymer film, usually blue or green, applied over a phosphate base. It gives a low, consistent coefficient of friction, so less torque is needed for the same bolt tension and the torque is set for the coated parts; it resists the atmosphere and chemical splash, and helps nuts come off at the next turnaround.

NO APPRECIABLE DIMENSIONAL CHANGE:DRAWING SIZES ARE THE SIZES AFTER COATINGBLACK OXIDEASEALER + OILSTEELLAYERS NOT TO SCALEDETAIL A · AT THE CREST · NOT TO SCALESEALER + OILDRAWING SIZESAME BEFORE AND AFTERBLACK OXIDEFORMED FROM THE STEEL SURFACESTEELBATH, ABOUT (MIL-DTL-13924)CLASS 1ALKALINE, BOILING285–305 °F (141–152 °C)CLASS 2ALKALINE CHROMATE250 ± 10 °F (121 ± 5 °C)CLASS 3FUSED SALT750–850 °F (399–454 °C)CLASS 4ALKALINE250–265 °F (121–130 °C)CLASS 1: CARBON AND LOW-ALLOY STEELCLASSES 2 TO 4: CORROSION-RESISTANT STEELFINISHBLACK OXIDESPECMIL-DTL-13924 · CLASSES 1 TO 4
A clean black finish without dimensional change

Black oxide

A chemical conversion of the steel surface to black iron oxide, sealed with oil or wax. It adds no thickness, so it suits precision parts and socket products, and gives a uniform dark appearance with light corrosion resistance indoors.

SEALANT / LUBRICANT (S, L)IF ORDEREDCONVERSION COATA CLEAR · C YELLOWAN–EN: NO HEXAVALENT CHROMIUMZINC · Fe/Zn 50.0002 IN. (5 µm) MINON SIGNIFICANT SURFACESMOST ZINC AT THE TIPBARREL PLATINGSTEELLEAST ZINC IN THE ROOTSLAYERS NOT TO SCALETHREAD ROOM · PITCH DIAMETERBASIC SIZECLASS 2A ALLOWANCEBOLT BEFORE PLATINGZINC ADDS ABOUT 4 × ITS THICKNESS (60°)F1941: PLATING ¼ OF ALLOWANCE AT MOST1/2-13: 0.000375 IN. MAX AT THE TIPPLATEBAKE IF OVER 39 HRCCONVERSION COATMIN 14 H TO 44 HRC, 24 H ABOVE, 375–425 °F (190–220 °C)ASTM B633: THE BAKE STARTS WITHIN 4 H OF PLATINGFINISHZINC ELECTROPLATINGSPECASTM F1941 (FASTENERS) · ASTM B633
Economical sacrificial protection for indoor and mild service

Zinc electroplating

A thin electroplated zinc layer with a clear, yellow or black chromate, or a chromium-free passivate. Zinc corrodes in preference to the steel underneath, so a scratch does not rust. It is the general-purpose finish for hardware that lives indoors or under cover.

Not sure which class the drawing means?

Send the drawing note and we will match it to a coating class · 832-446-3442